City Light Continues Utility Pole Upgrades for Advanced Metering

From late March and April 2017, Seattle City Light will continue supporting Advanced Metering services throughout the utility’s service territory by replacing existing utility poles with taller poles, which will host wireless utility data collection equipment.

The new poles will be 70 feet tall, which is about 20 feet taller than the existing poles. This project is part of the communications network to support Advanced Metering, which will automate meter reading and enable enhanced services.

Rendering of wireless utility data equipment on a utility pole.

From late March to April 2017, City Light crews will be replacing poles in the following areas:

  • Columbia City
  • View Ridge
  • Magnolia
  • Wallingford
  • Bitter Lake

View the March/April 2017 Utility Pole Maps for approximate construction work areas. Additional maps will be added on the Utility Pole Upgrade website as the project progresses into other areas within City Light’s service territory.

There are no maintenance power outages planned for this work. Some traffic and parking impacts are expected in the immediate work areas. Crews will be careful to maintain access to driveways.

Daily work hours are from Monday to Friday, 8:30 a.m. to 4:30 p.m. In most instances, the work to transfer existing equipment and install the data collection equipment can be completed in one day.

Customers can contact JoAnna Perley, Advanced Metering Deployment Manager at (206) 733-9648 or JoAnna.Perley@seattle.gov.

Visit the following websites for more information:

Seattle City Light’s “At Work in Your Neighborhood” website
www.seattle.gov/light/atwork

Seattle City Light’s Advanced Metering Program website
www.seattle.gov/light/meters

Advanced Metering Utility Pole Upgrades Continue in March 2017

In March 2017, Seattle City Light will continue supporting Advanced Metering services throughout the utility’s service territory by replacing existing utility poles with taller poles, which will host wireless utility data collection equipment. The new poles will be 70 feet tall, which is about 20 feet taller than the existing poles.

Rendering of wireless utility data equipment on a utility pole.

This project is part of the communications network to support Advanced Metering, which will automate meter reading and enable enhanced services.

Throughout the month of March, City Light crews will be replacing poles in the following areas:

  • Queen Anne (Galer Street)
  • Ballard (NW 46th Street)
  • Whittier Heights (8th Avenue NW)
  • Ravenna (NE 50th Street)

View the March 2017 Utility Pole Upgrade maps for approximate construction work areas. Additional maps will be added on the Utility Pole Upgrade website as the project progresses into other areas within City Light’s service territory.

There are no maintenance power outages planned for this work. Some traffic and parking impacts are expected in the immediate work areas. Crews will be careful to maintain access to driveways.

Daily work hours are from Monday to Friday, 8:30 a.m. to 4:30 p.m. In most instances, the work to transfer existing equipment and install the data collection equipment can be completed in one day.

Customers can contact JoAnna Perley, Advanced Metering Deployment Manager at (206) 733-9648 or JoAnna.Perley@seattle.gov.

Visit the following websites for more information:

Seattle City Light’s “At Work in Your Neighborhood” website
www.seattle.gov/light/atwork

Seattle City Light’s Advanced Metering Program website
www.seattle.gov/light/meters

Advanced Metering Utility Pole Upgrades Planned for February 2017

In February 2017, Seattle City Light will continue supporting Advanced Metering services throughout the utility’s service territory by replacing existing utility poles with taller poles, which will host wireless utility data collection equipment. The new poles will be 70 feet tall, which is about 20 feet taller than the existing poles.

Rendering of wireless utility data equipment on a utility pole.

This project is part of the communications network to support Advanced Metering, which will automate meter reading and enable enhanced services.

Throughout the month of February, City Light crews will be replacing poles in the following areas:

  • Lake City / North Seattle (NE 125th Street)
  • South Lake Union (Pontius Avenue N)
  • Othello Park (43rd Avenue S)
  • West Seattle / Junction (SW Edmunds Street)

View the February 2017 Utility Pole Upgrade maps for approximate construction work areas. Additional maps will be added on the Utility Pole Upgrade website as the project progresses into other areas within City Light’s service territory.

There are no maintenance power outages planned for this work. Some traffic and parking impacts are expected in the immediate work areas. Crews will be careful to maintain access to driveways.

Daily work hours are from Monday to Friday, 8:30 a.m. to 4:30 p.m. In most instances, the work to transfer existing equipment and install the data collection equipment can be completed in one day.

Customers can contact JoAnna Perley, Advanced Metering Deployment Manager at (206) 733-9648 or JoAnna.Perley@seattle.gov.


Visit the following websites for more information:

Seattle City Light’s “At Work in Your Neighborhood” website
www.seattle.gov/light/atwork

Seattle City Light’s Advanced Metering Program website
www.seattle.gov/light/meters

City Light Continues Utility Pole Upgrades for Advanced Metering

In January 2017, Seattle City Light will continue supporting Advanced Metering services throughout the utility’s service territory by replacing existing utility poles with taller poles, which will host wireless utility data collection equipment. The new poles will be 70 feet tall, which is about 20 feet taller than the existing poles.

Rendering of wireless utility data equipment on a utility pole.

This project is part of the communications network to support Advanced Metering, which will automate meter reading and enable enhanced services.

Throughout the month of January 2017, City Light crews will be replacing poles in the following areas:

  • Beacon Hill / Rainier Vista (S Columbian Way)
  • West Seattle / Delridge  (16th Ave SW)
  • West Seattle / High Point (26th Ave SW)
  • West Seattle / North Admiral (45th Ave SW)
  • Central District (24th Ave)

View the January 2017 Utility Pole Upgrade maps for approximate construction work areas. More maps will be added on the Utility Pole Upgrade website as the project progresses into other areas within City Light’s service territory.

There are no maintenance power outages planned for this work. Some traffic and parking impacts are expected in the immediate work areas. Crews will be careful to maintain access to driveways.

Daily work hours are from Monday to Friday, 8:30 a.m. to 4:30 p.m. In most instances, the work to transfer existing equipment and install the data collection equipment can be completed in one day.

Customers can contact JoAnna Perley, Advanced Metering Deployment Manager at (206) 733-9648 or JoAnna.Perley@seattle.gov.


Visit the following websites for more information:

Seattle City Light’s “At Work in Your Neighborhood” website
www.seattle.gov/light/atwork

Seattle City Light’s Advanced Metering Program website
www.seattle.gov/light/meters

City Light to Upgrade Utility Poles in Support of Advanced Metering

Starting in December 2016, Seattle City Light will be supporting Advanced Metering services throughout the utility’s service territory by replacing existing utility poles with taller poles, which will host wireless utility data collection equipment. The new poles will be 70 feet tall, which is about 20 feet taller than the existing poles.

Rendering of wireless utility data equipment on a utility pole.

This project is part of the communications network to support Advanced Metering, which will automate meter reading and enable enhanced services.

View the December 2016 Utility Pole Upgrade maps for approximate construction work areas. More maps will be added on the Utility Pole Upgrade website as the project progresses into other areas within City Light’s service territory.

There are no maintenance power outages planned for this work. Some traffic and parking impacts are expected in the immediate work areas. Crews will be careful to maintain access to driveways.

Daily work hours are from Monday to Friday, 8:30 a.m. to 4:30 p.m. In most instances, the work to transfer existing equipment and install the data collection equipment can be completed in one day.

Customers can contact JoAnna Perley, Advanced Metering Deployment Manager at (206) 733-9648 or JoAnna.Perley@seattle.gov.


Visit the following websites for more information:

Seattle City Light’s “At Work in Your Neighborhood” website
www.seattle.gov/light/atwork

Seattle City Light’s Advanced Metering Program website
www.seattle.gov/light/meters