Type of Permit Goal Nov. 2017 Performance
Simple Building IP* 80% in 48 Hours 90.1%
Medium Construction IP 80% in 2 Weeks 50%
Complex Construction IP 80% in 8 Weeks 68.5%
Construction Issuance 90% in 120 Days 88.6%
Master Use Permit Decisions 80% in 120 Days 71.4%

*IP: Initial Plan Review by SDCI staff

May Permit Turnaround Times

We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal May 2017 Performance
Simple Building IP* 80% in 48 Hours 97.6%
Medium Construction IP 80% in 2 Weeks 19.7% (80.9% in 5 wks)
Complex Construction IP 80% in 8 Weeks 48.5%
Construction Issuance 90% in 120 Days 90.3%
Master Use Permit Decisions 80% in 120 Days 52.8%

*IP: Initial Plan Review by SDCI staff

February Turnaround Times

Seattle DCI is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal Feb. 2016 Performance
Simple Building IP* 80% in 48 Hours 98.5%
Medium Construction IP 80% in 2 Weeks 20.3% (27.3% in 3 wks)
Complex Construction IP 80% in 8 Weeks 56.8%
Construction Issuance 90% in 120 Days 86.9%
Master Use Permit Decisions 80% in 120 Days 77.8%

*IP: Initial Plan Review by Seattle DCI staff

February Permit Turnaround Times

DPD is committed to providing good customer service to its applicants.  The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal Feb. 2014 Performance
Simple Building IP* 80% in 48 Hours  97.4%
Medium Construction IP 80% in 2 Weeks  77.7%
Complex Construction IP 80% in 8 Weeks  67.4%
Construction Issuance 90% in 120 Days  89.5%
Master Use Permit Decisions 80% in 120 Days  89.7%

*IP: Initial Plan Review by DPD staff