June 2014 Permit Turnaround Times

DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal June 2014 Performance
Simple Building IP* 80% in 48 Hours 95.5%
Medium Construction IP 80% in 2 Weeks 49.7% (83.6% in 3 weeks)
Complex Construction IP 90% in 8 Weeks 65.3%
Construction Issuance 90% in 120 Days  92.1%
Master Use Permit Decisions 80% in 120 Days  83.3%

*IP: Initial Plan Review by DPD staff

May 2014 Permit Turnaround Times

DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal May 2014 Performance
Simple Building IP* 80% in 48 Hours 94.90%
Medium Construction IP 80% in 2 Weeks 53.8% (86.2% in 3 weeks)
Complex Construction IP 90% in 8 Weeks 68.7%
Construction Issuance 90% in 120 Days  91.4%
Master Use Permit Decisions 80% in 120 Days  83.6%

*IP: Initial Plan Review by DPD staff

April 2014 Permit Turnaround Times

DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal April 2014 Performance
Simple Building IP* 80% in 48 Hours 95.3 %
Medium Construction IP 80% in 2 Weeks 77.3%
Complex Construction IP 90% in 8 Weeks 69.6%
Construction Issuance 90% in 120 Days 93.1%
Master Use Permit Decisions 80% in 120 Days 90.9%

*IP: Initial Plan Review by DPD staff

March Permit Turnaround Times

DPD is committed to providing good customer service to its applicants.  The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal Mar. 2014 Performance
Simple Building IP* 80% in 48 Hours  97.2%
Medium Construction IP 80% in 2 Weeks  62.8%
Complex Construction IP 80% in 8 Weeks  59.1%
Construction Issuance 90% in 120 Days  86.5%
Master Use Permit Decisions 80% in 120 Days  91.4%

*IP: Initial Plan Review by DPD staff