November Permit Turnaround Times

DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal Nov. 2014 Performance
Simple Building IP* 80% in 48 Hours 95.0%
Medium Construction IP 80% in 2 Weeks 76.7%
Complex Construction IP 90% in 8 Weeks 68.5%
Construction Issuance 90% in 120 Days  90.1%
Master Use Permit Decisions 80% in 120 Days  81.4%

*IP: Initial Plan Review by DPD staff

October Permit Turnaround Times

DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal Oct. 2014 Performance
Simple Building IP* 80% in 48 Hours 97.9%
Medium Construction IP 80% in 2 Weeks 66.2%
Complex Construction IP 90% in 8 Weeks 81.0%
Construction Issuance 90% in 120 Days  89.6%
Master Use Permit Decisions 80% in 120 Days  81.7%

*IP: Initial Plan Review by DPD staff

September Permit Turnaround Times

DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal Sept. 2014 Performance
Simple Building IP* 80% in 48 Hours 96.3%
Medium Construction IP 80% in 2 Weeks 70.9%
Complex Construction IP 90% in 8 Weeks 71.8%
Construction Issuance 90% in 120 Days 92.8%
Master Use Permit Decisions 80% in 120 Days 86.4%

*IP: Initial Plan Review by DPD staff

August Permit Turnaround Times

DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal Aug. 2014 Performance
Simple Building IP* 80% in 48 Hours 95.9%
Medium Construction IP 80% in 2 Weeks 71.1%
Complex Construction IP 90% in 8 Weeks 60.8%
Construction Issuance 90% in 120 Days  91.2%
Master Use Permit Decisions 80% in 120 Days  81.4%

*IP: Initial Plan Review by DPD staff

July 2014 Permit Turnaround Times

DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal July 2014 Performance
Simple Building IP* 80% in 48 Hours 95.1%
Medium Construction IP 80% in 2 Weeks 50.5% (81.3% in 3 weeks)
Complex Construction IP 90% in 8 Weeks 59.4%
Construction Issuance 90% in 120 Days  104.0%
Master Use Permit Decisions 80% in 120 Days  85.1%

 

*IP: Initial Plan Review by DPD staff