July Permit Turnaround Times

We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal July 2017 Performance
Simple Building IP* 80% in 48 Hours 96.7%
Medium Construction IP 80% in 2 Weeks 12.4% (81.6% in 5 wks)
Complex Construction IP 80% in 8 Weeks 35.2%
Construction Issuance 90% in 120 Days 79.2%
Master Use Permit Decisions 80% in 120 Days 54.1%

*IP: Initial Plan Review by SDCI staff

April Permit Turnaround Times

We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal April 2017 Performance
Simple Building IP* 80% in 48 Hours 97.7%
Medium Construction IP 80% in 2 Weeks 14.0% (77.5% in 5 wks)
Complex Construction IP 80% in 8 Weeks 32.1%
Construction Issuance 90% in 120 Days 89.3%
Master Use Permit Decisions 80% in 120 Days 65.7%

*IP: Initial Plan Review by SDCI staff

February Permit Turnaround Times

We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal Feb. 2017 Performance
Simple Building IP* 80% in 48 Hours 96.6%
Medium Construction IP 80% in 2 Weeks 17.1% (66.2% in 3 wks)
Complex Construction IP 80% in 8 Weeks 44.0%
Construction Issuance 90% in 120 Days 70.3%
Master Use Permit Decisions 80% in 120 Days 68.8%

*IP: Initial Plan Review by SDCI staff

Permit Turnaround Times

We are committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

 

Type of Permit Goal Jan. 2017 Performance
Simple Building IP* 80% in 48 Hours 99.3%
Medium Construction IP 80% in 2 Weeks 11.6% (76.5% in 5 wks)
Complex Construction IP 80% in 8 Weeks 48.2%
Construction Issuance 90% in 120 Days 80.5%
Master Use Permit Decisions 80% in 120 Days 73.4%

*IP: Initial Plan Review by SDCI staff

December Permit Turnaround Times

We are committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

 

Type of Permit Goal Dec. 2016 Performance
Simple Building IP* 80% in 48 Hours 97.9%
Medium Construction IP 80% in 2 Weeks 25.1% (44.7% in 3 wks)
Complex Construction IP 80% in 8 Weeks 57.9%
Construction Issuance 90% in 120 Days 81.2%
Master Use Permit Decisions 80% in 120 Days 72.0%

*IP: Initial Plan Review by Seattle DCI staff