April Permit Turnaround Times

We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal April 2018 Performance
Simple Building IP* 80% in 48 Hours 94.3%
Medium Construction IP 80% in 2 Weeks 20.7%  (78.2% in 3 wks)
Complex Construction IP 80% in 8 Weeks 69.2%
Construction Issuance 90% in 120 Days 86.9%
Master Use Permit Decisions 80% in 120 Days 54.5%

*IP: Initial Plan Review by SDCI staff

February Permit Turnaround Times

We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal Feb. 2018 Performance
Simple Building IP* 80% in 48 Hours 97.1%
Medium Construction IP 80% in 2 Weeks 30.5%
Complex Construction IP 80% in 8 Weeks 50.0%
Construction Issuance 90% in 120 Days 84.7%
Master Use Permit Decisions 80% in 120 Days 61.2%

*IP: Initial Plan Review by SDCI staff

December Permit Turnaround Times

We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal Dec. 2017 Performance
Simple Building IP* 80% in 48 Hours 96.3%
Medium Construction IP 80% in 2 Weeks 37.2%
Complex Construction IP 80% in 8 Weeks 61.5%
Construction Issuance 90% in 120 Days 89.6%
Master Use Permit Decisions 80% in 120 Days 62.5%

*IP: Initial Plan Review by SDCI staff

September Permit Turnaround Times

We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal Sept. 2017 Performance
Simple Building IP* 80% in 48 Hours 97.1%
Medium Construction IP 80% in 2 Weeks 43.17% (85.4% in 5 wks)
Complex Construction IP 80% in 8 Weeks 56.0%
Construction Issuance 90% in 120 Days 85.5%
Master Use Permit Decisions 80% in 120 Days 66.7%

*IP: Initial Plan Review by SDCI staff

August Permit Turnaround Times

We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal August 2017 Performance
Simple Building IP* 80% in 48 Hours 95.48%
Medium Construction IP 80% in 2 Weeks 22.37% (95.4% in 5 wks)
Complex Construction IP 80% in 8 Weeks 53.80%
Construction Issuance 90% in 120 Days 82.16%
Master Use Permit Decisions 80% in 120 Days 75.81%

*IP: Initial Plan Review by SDCI staff