October Permit Turnaround Times

Seattle DCI is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal October 2016 Performance
Simple Building IP* 80% in 48 Hours 95.9%
Medium Construction IP 80% in 2 Weeks 71.0%
Complex Construction IP 80% in 8 Weeks 81.0%
Construction Issuance 90% in 120 Days 90.5%
Master Use Permit Decisions 80% in 120 Days 65.6%

*IP: Initial Plan Review by Seattle DCI staff

July Permit Turnaround Times

We are committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed atwww.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal July 2016 Performance
Simple Building IP* 80% in 48 Hours 96.20%
Medium Construction IP 80% in 2 Weeks 53.87%
Complex Construction IP 80% in 8 Weeks 72.37%
Construction Issuance 90% in 120 Days 89.48%
Master Use Permit Decisions 80% in 120 Days 80.65%