Arbor Heights Safe Routes to School

New asphalt edging along 35th Ave SW, for smooth transition from curb.

 

Work on the Arbor Heights Safe Routes to School project continues next week, as the team deals with a shortage of both concrete and the trucks required to transport it.

 

This week the team:

  • Poured concrete on all driveways along west side of 35th Ave SW (SW 100th – SW 106th)
  • Built most of the ADA curb ramps on 35th Ave SW (SW 100th – SW 104th)
  • Began pouring concrete to complete curb bulbs

 

Next week crews are scheduled to:

  • Complete asphalt paving on the east side of 35th Ave SW (SW 100th – SW 102nd & at SW 106th)
  • Complete pouring concrete to finish ADA compliant curb ramps
  • Install roadway markings on 35th Ave SW
  • Pour concrete for sidewalks on west side of 35th Ave SW

 

What you can expect:

August 13-17 | 7 AM – 5 PM

Closure

  • 35th Ave SW will be fully closed between SW 100th and SW 104th streets during work hours.

 

Tuesday, August 14 | 9 AM – 12 PM

Closure

  • Residents on the east side of 35th Ave SW, SW 100th – SW 102ndthe asphalt work may impact your driveway access 8/14 for up to 1 hour, between 9 AM and 12 PM. Steel plates will be placed while asphalt hardens.

 

Note: 35th Ave SW will reopen at the end of each work day, and remains open during the weekend.

 

Thank you for your understanding as project work continues!