December Permit Turnaround Times

We are committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

 

Type of Permit Goal Dec. 2016 Performance
Simple Building IP* 80% in 48 Hours 97.9%
Medium Construction IP 80% in 2 Weeks 25.1% (44.7% in 3 wks)
Complex Construction IP 80% in 8 Weeks 57.9%
Construction Issuance 90% in 120 Days 81.2%
Master Use Permit Decisions 80% in 120 Days 72.0%

*IP: Initial Plan Review by Seattle DCI staff