November Permit Turnaround Times

We are committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

 

Type of Permit Goal Nov. 2016 Performance
Simple Building IP* 80% in 48 Hours 95.6%
Medium Construction IP 80% in 2 Weeks 55.1%
Complex Construction IP 80% in 8 Weeks 77.0%
Construction Issuance 90% in 120 Days 89.8%
Master Use Permit Decisions 80% in 120 Days 64.8%

*IP: Initial Plan Review by Seattle DCI staff