July Permit Turnaround Times

We are committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed atwww.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).

Type of Permit Goal July 2016 Performance
Simple Building IP* 80% in 48 Hours 96.20%
Medium Construction IP 80% in 2 Weeks 53.87%
Complex Construction IP 80% in 8 Weeks 72.37%
Construction Issuance 90% in 120 Days 89.48%
Master Use Permit Decisions 80% in 120 Days 80.65%

*IP: Initial Plan Review by Seattle DCI staff