Update: Stone Way N closure at N 34th will continue through Nov. 7

Seattle Public Utilities

Note: Due to weather and utility work, drainage installation at Stone Way North and North 34th Street will continue through Nov. 7.

The North Transfer Station project is installing drainage systems at Stone Way North and North 34th Street. This will involve 24-hour closure of Stone Way North over multiple days. It will also involve a partial closure along the north side of North 34th Street during work hours.

Schedule of Closures

  • Week of Nov. 3 – Close Stone Way North between North 34th and 35th Streets for daytime excavation work. Closure will be 24-hours and includes the city sidewalk during daytime hours in front of the Brooks building on Stone Way North and North 34th Street to install drainage systems
  • Week of Nov. 10 and Nov. 17 – Partially close the north side of North 34th Street during daytime hours to install drainage systems
  • Week of Nov. 17 – Restore sidewalk in front of Brooks building

To minimize impacts, crews will conduct work during daytime hours from 7 am – 6 pm.  Pedestrian ramps and re-routing will allow access to the adjacent buildings and businesses. “No-Park” signs will be placed near Stone Way North and North 34th Street prior to the work.  The work areas will be fenced off for public safety.

For more information about the project, email the project team at SPU_NTS@seattle.gov, call the project hotline at 206-819-5948 or visit the project website at www.seattle.gov/util/NewNorth.