Construction at a glance
UW | Capitol Hill | |
Demolition | 100% | 100% |
Station Excavation | 100% | 100% |
Tunnel construction – TBM mining | 100% | 100% |
Tunnel Construction – Cross Passage Excavation and Lining | 100% | 100% |
Station construction | 98% | 71% |
Power Systems & Track (overall) – 49.5% | 49.5% | 49.5% |
U-Link Overall 88.9% |
*As of August 31, 2014