Street closures at Stone Way N and N 34th Street delayed to week of Oct 13

Note: Drainage installation at Stone Way North and North 34th Street has been delayed for one week to Oct 13 as construction crews encountered underground obstruction while removing groundwater.

Starting the week of Oct. 13, the North Transfer Station project will begin installing drainage systems at Stone Way North and North 34th Street. This will involve 24-

Schedule of Closures

  • Week of Oct 13 – Stone Way North just north of North 34th Street will be closed for daytime excavation work. Closure will be 24-hours and will last up to five days.
  • Week of Oct 20 – Sidewalk in front of the Brooks Building on Stone Way North and North 34th Street will be closed during daytime hours to install drainage systems.
  • Week of Oct 27 – North side of North 34th Street will be partially closed during daytime hours to install drainage systems.
  • Week of Nov 3 – Sidewalk in front of Brooks Building will be restored.

To minimize impacts, crews will conduct work during daytime hours from 7 am – 6 pm.  Pedestrian ramps and re-routing will allow access to the adjacent buildings and businesses.  “No-Park” signs will be placed near Stone Way North and North 34th Street prior to the work.  The work areas will be fenced off for public safety.

For more information about the project, email the project team at SPU_NTS@seattle.gov, call the project hotline at 206-819-5948 or visit the project website at www.seattle.gov/util/NewNorth.