March Permit Turnaround Times

DPD is committed to providing good customer service to its applicants.  The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).

Type of Permit Goal Mar. 2014 Performance
Simple Building IP* 80% in 48 Hours  97.2%
Medium Construction IP 80% in 2 Weeks  62.8%
Complex Construction IP 80% in 8 Weeks  59.1%
Construction Issuance 90% in 120 Days  86.5%
Master Use Permit Decisions 80% in 120 Days  91.4%

*IP: Initial Plan Review by DPD staff